Posted on: April 23, 2021

Northside Drainage Improvements Project Construction Begins

Brownsburg placeholder

The contractor for the Northside Drainage Improvements project will be mobilizing on April 28, 2021 through May 4, 2021 and will begin construction on May 5, 2021 through December 2021 with landscaping to be completed in the spring of 2022. The roads listed below will have restrictions or closed during the construction time.  

This will be a lengthy major project and will appreciate your time and patience during construction.  

Schedule dates may change due to weather and unknown site conditions discovered during construction.


Contract A Areas:

Jefferson St. - May 5-September 16

Parthenia Ave. - May 5-September 3

Adams St. - May 5-August 30

Grant St. - June 1-November 2


Contract B Areas:

Jefferson St. - July 1-November 15

Vermont St. - September 24-December 2

Copeland. - October 11-November 22

Adams St. - October 25-November 26

Railroad St. - November 18-November 19